According to OPNAV 3110.11, when should an aircraft service period adjustment evaluation occur?

Prepare for the Maintenance/Production Control Exam. Use flashcards and multiple-choice questions, each with hints and explanations, to enhance your learning. Get equipped and excel in your exam!

The correct timing for an aircraft service period adjustment evaluation, as specified in OPNAV 3110.11, is 6 months before and 3 months after the completion of the expected maintenance or service period. This timeline is crucial as it allows for comprehensive assessments and adjustments to be made regarding the aircraft’s readiness, maintenance status, and operational needs.

Conducting the evaluation 6 months prior ensures that any potential issues can be identified early, allowing for appropriate planning and resource allocation. Evaluating 3 months after completion helps capture any wear and tear that may have developed during the service period, ensuring ongoing operational efficiency and safety. This dual timeframe approach is designed to enhance fleet readiness and mitigate risks associated with aircraft maintenance.

Other choices represent timeframes that either do not provide sufficient lead time for proactive assessments or may miss critical follow-up evaluations that help maintain the aircraft's operational integrity post-service period. Thus, the selected timeframe is the most effective for aligning maintenance practices with operational requirements.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy